Material Landing Planner

When must each material be ordered — and when must it sail from a Vietnamese port — to land on your site on time? Enter your foundation completion date; we work everything backwards from a typical construction sequence. Adjust any assumption to match your programme.

Indicative planning tool. Production and freight times vary by product, season and carrier — have our desk verify the plan before you commit a programme to it.

⚙️ Adjust material groups & assumptions (weeks after foundation, production days...)
IncludeMaterial groupNeeded on site (weeks after foundation)Production (days)
Fiber cement boards
Aluminum & glass systems
Porcelain & large-format tiles
Sanitary ware & fittings
Quartz surfaces (cut-to-size)
Engineered wood & plywood
Material group🛒 Order by🏭 Ex-factory🚢 Must sail from VN⚓ ETA dest. port🏗️ On site
Fiber cement boards5 Aug 202631 Aug 20266 Sept 202627 Sept 202613 Oct 2026
Aluminum & glass systems26 Jul 202614 Sept 202620 Sept 202611 Oct 202627 Oct 2026
Porcelain & large-format tiles9 Sept 202612 Oct 202618 Oct 20268 Nov 202624 Nov 2026
Sanitary ware & fittings5 Oct 20269 Nov 202615 Nov 20266 Dec 202622 Dec 2026
Quartz surfaces (cut-to-size)5 Oct 20269 Nov 202615 Nov 20266 Dec 202622 Dec 2026
Engineered wood & plywood24 Oct 202623 Nov 202629 Nov 202620 Dec 20265 Jan 2027
Order & depositProductionTo VN port & docsSea freightCustoms, delivery & buffer

Fiber cement boards

order 5 Aug 2026sails 6 Sept 2026on site 13 Oct 2026

Aluminum & glass systems

order 26 Jul 2026sails 20 Sept 2026on site 27 Oct 2026

Porcelain & large-format tiles

order 9 Sept 2026sails 18 Oct 2026on site 24 Nov 2026

Sanitary ware & fittings

order 5 Oct 2026sails 15 Nov 2026on site 22 Dec 2026

Quartz surfaces (cut-to-size)

order 5 Oct 2026sails 15 Nov 2026on site 22 Dec 2026

Engineered wood & plywood

order 24 Oct 2026sails 29 Nov 2026on site 5 Jan 2027
Turn it into a real quote → submit your BOM